Work Order Quote and Change Order Controls Playbook

Install intake, approvals, not-to-exceed rules, and change order governance so reactive work does not become runaway spend.

Run the OperationCorePlaybook60 minProcurement and Ops, Finance

Reactive work is where spend runs away.

This playbook installs a tight workflow so:

  • every job has an owner and a not-to-exceed cap
  • after-hours and emergency work uses explicit approvals
  • scope creep requires a documented change order
  • invoices match the work order and acceptance evidence

What you will produce

  1. Work order intake form and required fields
  2. Quote request and approval workflow
  3. Not-to-exceed rules and exception handling
  4. Change order governance rules
  5. Invoice matching checklist

Step-by-step implementation

Step 1: Standardize work order intake

Work order intake form (copy and paste)

Copyable template (TEXT)

Work Order Intake

Request date:
Site:
Location detail:
Work type:
Issue description:
Safety or risk flag: [yes/no]
Requested completion date:
Vendor (if known):
Owner:
Not-to-exceed cap:
After-hours approved: [yes/no]
Approval reference:

Step 2: Require quotes above a threshold

Quote request template (copy and paste)

Copyable template (TEXT)

Quote Request

Work order ID:
Scope summary:
Requested schedule:
Pricing format required:
- Labor by role and hours
- Materials list with unit pricing
- Any trip charge or after-hours premium separately stated
Not-to-exceed requested:
Proof requirements:

Step 3: Set not-to-exceed rules

Not-to-exceed policy (copy and paste)

Copyable template (TEXT)

Not-to-Exceed Rules

- All work orders must have an NTE cap unless exempted.
- Any work expected to exceed the NTE requires a documented change order before proceeding.
- After-hours or emergency premiums require explicit approval and must reference the approval on the invoice.
- Work performed without approvals may be disputed or denied.

Step 4: Change order governance

Change order template (copy and paste)

Copyable template (TEXT)

Change Order

Work order ID:
Reason for change:
New scope:
Incremental cost:
Updated not-to-exceed:
Schedule impact:
Approved by:
Approval date:

Step 5: Invoice matching checklist

Invoice matching checklist (copy and paste)

Copyable template (TEXT)

Invoice Matching Checklist

- Work order ID present on invoice
- Scope aligns to approved quote or rate card
- Not-to-exceed not exceeded without approved change order
- After-hours premiums documented and approved
- Parts and materials markup complies with policy
- Proof of work attached (photos, logs, completion notes)
- Acceptance recorded (inspection or sign-off)

Common failure modes

  • no NTE cap, so scope expands without friction
  • emergency work becomes a loophole for premium pricing
  • change orders happen verbally, so Finance cannot enforce
  • invoices do not reference work order IDs, so matching fails

Change log

v1.0 (2026-02): Latest release